|
PROJECT: Courtrooms #1 & #2
REPORT NO. 1
Mercer County Courthouse
Mercer,
Pennsylvania
DATE July 19,2000 TIME 10:00
a.m.
PRESENT AT MEETING Lou DeJulia - Mercer
County Maintenance
Doug Wallace - Wallace Builders
Denny Salmon - Wallace Builders
Chip
Smith - Easley & Rivers
Larry
Schrock - Federal Iron
Bob
Mastriana - 4M Company
NOTES
- An emergency meeting was held at courtroom #2 to determine
the extent of damage and to plan the re- pair and stabilization of the
plaster ceiling beams.
- The scope of work to repair the beams will be based on the
direction discussed at our job meeting. Specifications and drawings to
document this will be prepared as soon as possible by the 4M Company.
- Wallace Builders will follow up with a proposal to the
county on Monday based on our discussions. Authorization from Lou to proceed
was granted and removal of a section of the ceiling beam in court- room #1
was to be done the following day.
- Easily & Rivers will also do the repair of the west
portico plaster cornice that was damaged due to water infiltration from the
faulty roof scupper. We had a prior estimate from another company to do the
re- pairs; however, since Easily & Rivers are doing the courtroom
repairs and already have scaffolding and plasterers on the job, they were
able to do the repairs for $750.00, saving the county approximately
$1200.00. They will enter into a separate purchase order directly with Lou
for these repairs.
- Lou and Bob then met with Commissioners Gene Brenneman and
Brian Shipley and Prosecutor Lou McEwen and Administrator Rick Boggs to
discuss the historical preservation approach we are going to take with the
courtroom plaster ceiling beam repairs.


PROJECT: Courtrooms #1 & #2
REPORT NO. 2
Mercer County Courthouse
Mercer, Pennsylvania
DATE July 25, 2000 TIME 2:00
p.m.
PRESENT AT MEETING Gene Brenneman - Mercer
County Commissioner
Brian Shipley
- Mercer County Commissioner
Rick Boggs - Chief Clerk
Lou
DeJulia - Mercer County Maintenance
Bob
Mastriana - 4M Company
NOTES
- A grant application prepared by 4M Company at the request
of the Commissioners was reviewed and discussed. Commissioner Shipley was
presenting the request for the matching grant to the Governor's office for
the courthouse restoration.
- 4M Company then presented Wallace Builder's proposal for
repair of the courtrooms decorative plaster ceiling beams. Discussion
followed and contracts were prepared along with a resolution authorizing
this to be on the agenda for the next Commissioner's meeting.
- See Wallace Builders proposal and the outline
specifications along with 4M's letter dated July 25,2000 preceding this
report.
- The steel is presently being fabricated and will be
delivered this coming Monday, July 31st with work to start at 4:00 p.m.
through 12:00 midnight. This schedule will be adhered too as to not disturb
the operations of the courthouse. Work is anticipated to be completed by
August 31,2000.
Wallace Builders
Douglas Wallace,
Partner
Telephone (724) 652-6175
Box 333 Pulaski, PA,
16143
Fax (724) 652-2333
PROPOSAL
DATE: July 24,2000
TO: 4M Company
4251 Glenwood Avenue
Boardman, OH 44512
RE: Repairs to existing beams
Courtrooms #1 and #2
Mercer County Courthouse
ATTN: Mr. Robert Mastriana
We hereby submit specifications and estimates
for: labor, material, and equipment to complete the following items of work:
-
Install approx. 1396 l.f. of steel plate
supports to all beams (see sketch by FIW).
-
Painting of steel plates only.
-
Replacement of approx. 40 l.f. (20' each
courtroom) decorative plaster beams.
-
Minor patching of finish on other beams (1
man 6 days).
-
Remove 40 light fixtures and 4 smoke
detectors.
-
Relocated 24 existing light fixtures and 4
smoke detectors as indicated on sketch.
-
Re-wire light fixtures as needed.
-
Cover up and clean up as required.
Total Budget Estimate:
$87,900.00
NOTES:
All work to be completed on second shift on a time and material basis.
Payments to be made as follows:
upon completion
Note: This proposal may be withdrawn by us
if not accepted within 30 days.
Rates Though June 1, 2001
For Mercer County Courthouse
| Labor Rates: Wallace
Builders |
|
Trade |
Regular |
Overtime |
Double Time |
Superintendent
Carpenter
Laborer
Operator
|
38.77
36.17
28.99
41.31
|
58.16
54.26
43.49
61.97
|
77.54
72.34
57.98
82.62
|
| Equipment Rates: Wallace
Builders |
|
Description |
Hourly Rate |
|
Pickup Truck
Dump Truck
Backhoe
Dozer
18T Crane
Gehl Lift
Bobcat Loader
|
10.00
15.00
30.00
25.00
45.00
30.00
25.00
|
| Markup Rates: PIC
Electric* |
|
Description |
Markup |
Labor
Material Purchases
Subcontracted Work
Small Tools (Less then $300.00 in value)
|
Cost plus 20%
Cost plus 20%
Cost plus 5%
3% of Labor Cost
|
| Labor Rates: PIC Electric* |
| Trade |
Regular |
Overtime |
Double Time |
Superintendent
Foreman
Journey Electrician
Apprentice Electrician
Service Man W/Truck
*plus 20% Overhead & Profit
|
50.00
39.55
37.80
30.15
50.00
|
75.00
59.33
56.70
45.23
75.00
|
100.00
79.10
75.60
60.30
100.00
|
| Labor Rates: Easley and Rivers* |
| Trade |
Regular |
Overtime |
Double Time |
Lather Foreman
Plasterer Foreman
Plasterer
Hod Carrier
*Plus 20% OH&P |
39.28
36.73
35.09
28.68
|
58.92
50.84
48.38
39.90
|
78.56
64.95
61.67
51.12
|
OUTLINE SPECIFICATIONS
FOR
MERCER COUNTY COURTHOUSE
COURTROOM CEILING BEAMS RESTORATION
July 28, 2000
GENERAL CONTRACTOR
The General Contractor shall provide labor, material, and
equipment to complete the following work:
- Provide temporary scaffolding and barriers as required to
complete work.
- The existing ceiling lights are to be removed from the
beams and placed in three symmetrical bay spacings totaling 12 lights
between the rows of beams. This will allow for the eventual replacement of
the fixtures with more appropriate historical chandeliers.
- Three continuous steel plates to secure the plaster beams
are to be installed using l/4" thick x 5-1/2" Wide x 14' length
flat bar with 3/8" diameter all-thread rods. The rods are to be
12" in length for the side moldings support plates and 18" for the
center beams support plate. They are to be shoe welded at 2'-0" o.c.
and provided with two interlocking nuts and one flat washer, installed with
a l/4" x 6" x 6" flat plate with a 7/16" diameter hole
centered in each plate to distribute the weight evenly along the attic
surface of the concrete deck.
- Every 2'-0" o.c., the attic concrete deck is to be
core drilled to allow for these structural
beam supports. The steel support plates are to be installed in the recessed
soffit panels on the four ceiling beams and also on the perimeter wall
cornice beam soffit panels. The perimeter wall cornice is also to be
inspected for any structural deterioration to the decorative dentil moldings
and brackets and to repair as required.
- All new plaster beams that are to replace the missing or
damaged beams are to match and replicate the existing profiles and moldings
of the existing plaster beams and to blend seamlessly with the original.
Only those portions of the existing plaster beams and moldings that are
structurally unsound and weakened beyond repair are to be replaced.
- All steel is to be shop primed gray and free of any surface
defects. Field paint all exposed faces to match existing color and finish of
the recessed soffits of the plaster beams after installation.
- Repair the existing damaged wood portions of the Judges
Bailiff's bench in Courtroom #2 and refinish to match existing.
- Because the Courthouse must remain open and the offices and
public undisturbed as much as possible, all work must be done after hours
from 4:00 p.m. to 12:00 a.m. Work commenced Thursday, July 20th and it is
anticipated to be completed August 30th, 2000. Because of the many
conditions regarding this type of work, an estimate will be provided for
budgetary purposes; however, the work will be done on a time and material
basis.
Back
to Main Page Next
|