|
PROJECT: Courtrooms #1 & #2
REPORT NO. 6
Mercer County Courthouse
Mercer, Pennsylvania
DATE August, 10, 2000 TIME
2:00 p.m.
PRESENT AT MEETING Pat Summers - Easily
& Rivers, Plasterer Superintendent
Lou
DeJulia - Mercer County Maintenance
Robert
A. Mastriana - 4M Company
NOTES
- Bob met with Lou to inspect the progress of the work.
Easily & Rivers had scaffolding delivered and were starting to erect it.
Pat Summers of Easily & Rivers said two latherers were coming Tuesday to
begin the plaster beams wire framing. We were not pleased with this
information since that is going to delay the completion of the plaster work.
Lou and Bob requested the latherers start working on Friday and work through
the weekend so by Monday the actual plaster can begin. This could save a
considerable amount of time and keep the work on schedule. Bob called Doug
at Wallace Builders to try to schedule this with Easily & Rivers.
Because of the type of plaster being used for the decorative beams, they can
be painted after only a couple of days of curing which will help expedite
the completion of their work.
- The painters have completed most of their work in Courtroom
#I and Wallace Builders has completed most of their steel work and have
started erecting the steel in Courtroom #2.
- Bob and Lou took Commissioner Gene Brenneman on a personal
tour of the work in the courtrooms to show him the progress.
PROJECT: Courtrooms #1
& #2
REPORT NO. 7
Mercer County Courthouse
Mercer, Pennsylvania
DATE August 15, 2000 TIME
1:30 p.m.
PRESENT AT MEETING Lou DeJulia -
Mercer County Maintenance
Robert A. Mastriana - 4 M Company
NOTES
- Lou and Bob met to review the progress of the construction.
The plasterers were completing the scratch coat on the wire lath form work
for the decorative plaster beam that was removed in Courtroom #2. The finish
coat should be completed by Friday in Courtroom #2 along with the lath and
scratch coat of plaster in Courtroom #2) s ceiling beam. All the steel work
has been completed except where the new plaster beams are located.
- It is anticipated that by next Wednesday all plaster work
will be done so that the courtrooms can be put back together and all the
walls) flooring, furniture, etc., can be cleaned.
- It was also requested by the Judges that they would like
their individual chambers professionally cleaned along with their courtrooms
due to all the construction debris.
- Wallace Builders has gotten an estimate to clean the
courtrooms and will get an additional estimate for their individual
chambers. The cleaning is tentatively scheduled for the week of August 28th
with completion by Labor Day.

PROJECT: Courtrooms #1
& #2
REPORT NO. 8
Mercer County Courthouse
Mercer, Pennsylvania
DATE August 17, 2000
TIME 4:00 p.m.
PRESENT AT MEETING Robert A Mastriana - 4M
Company
NOTES
-
Bob went to the courtrooms to inspect the
work. Since only the finish work remains, the work men are working days
instead of evenings.
-
Electricians need to finish ceiling lights in
Courtroom #2 and check wiring on bailiffs bench to make sure everything is
operating due to damage caused by beam collapse.
-
The plaster scratch coat is starting now that
the wire lath is complete in Courtroom #2. Plasterers should be starting
finish molding plaster on beams in both courtrooms in the next couple of
days.
-
Wallace Builders is having Greenville Lumber
re-build bailiff bench's wood top and moldings so it can be finished to
match existing woodwork. Painters should finish their work by next Friday.
-
Bob talked to Denny Salmon of Wallace
Builders to verify completion of work. Next Thursday and Fri- day, they are
going to clean the Judges' chambers and then on Monday start in the
courtrooms. The cost of cleaning the Judges' chambers is $750 each x 2 =
$1500. The cost to clean the courtrooms is $4700. The total cost is $6200,
which mayor may not be able to be absorbed in the original time &
material budget. We won't know for sure until all the costs are complete.
-
Bob met with Rick Boggs to discuss contracts
and have them placed on the agenda for the next Commissioners' meeting to
approve and sign so that when work is completed at the end of the month,
they can be paid.
Back
to Main Page Next
|