|
PROJECT:
Courtrooms #1 & #2
REPORT NO. 9
Mercer County Courthouse
Mercer, Pennsylvania
DATE August 21, 2000 TIME
11:15 am
PRESENT AT MEETING Lou DeJulia
- Mercer County Maintenance
Robert
A Mastriana - 4M Company
NOTES
- Bob met with Lou to review progress of construction. The
finish plaster is being installed on Courtroom #1' s ceiling beams. The
lights are complete in Courtroom #2. Everything is proceeding on schedule as
previously reported. They are working this weekend to ensure the schedule is
adhered to.
- All work including cleaning will be done by Labor Day.
- Bob met with Rick Boggs and Commissioner Brian Shipley to
verify contracts being signed this Thursday at the Commissioners' meeting.
PROJECT: Courtrooms #1 &
#2
REPORT NO. 10
Mercer County Courthouse
Mercer, Pennsylvania
DATE August 25,
2000 TIME 4:00 pm
PRESENT AT MEETING Denny Salmon -
Wallace Builders
Robert A. Mastriana - 4M Company
NOTES
- Bob met with Denny to go over completion of work and
schedule for this weekend.
- The plasterers finished installing the decorative plaster
molding on the new beam in Courtroom # 1, and the steel is being completed
also. The painters were going to finish painting the beam Saturday morning,
and Wallace Builders will begin dismantling the scaffolding and removing the
visqueen immediately thereafter.
- In Courtroom #2, the plasterers were just starting to
install the decorative molding and would be completed later that evening.
- Denny was going to work with the men throughout the weekend
to ensure the completion of their work.
The cleaning crew was completing the Judges' chambers and will begin in the
courtrooms Monday. Everything is on schedule as planned.

PROJECT: Courtrooms #1 &
#2
REPORT NO. 11
Mercer County Courthouse
Mercer, Pennsylvania
DATE September 1, 2000 TIME
11:30 am
PRESENT AT MEETING Denny Salmon - Wallace Builders
NOTES
- Everything has been completed regarding the Courtrooms
repair work.
- The substantial completion date will be September 1,2000.
Everything went according to plan, on-schedule, and on-budget. Even the
exterior plaster repair on the west portico is done.
- 4M has completed the final paperwork and has submitted it
to Wallace Builders to sign and notarize. They will include these release
forms with their one and only Application for Payment to 4M for approval. 4M
will submit them to Lou next week after they are certified.
- Wallace Builders and the entire team did an outstanding
job, and they are to be congratulated. Actual work was started on Monday
evening, July 31st and was completed on Thursday evening, August 31st.
- The cooperative team approach with Wallace Builders, the
subcontractors, and Lou DeJulia were the reasons for this success.

Back
to Main Page |