PROJECT: North & West Portico Restoration
REPORT NO. 21
Mercer County Courthouse
Mercer, Pennsylvania
DATE September 2, 1999 TIME
10:00 a.m.
PRESENT AT MEETING Kevin Klosky - Keystone
Waterproofing
Lou DeJulia - Mercer County Maintenance
Bob
Mastriana - 4M Company
NOTES
GENERAL
- Bob reviewed with Lou the shop drawings for the historic
railings and approved the changes as noted. They were mailed to Federal Iron
to begin fabrication.
- Easily & Rivers had an additional plasterer on the job
to help expedite completing their scope of work.
- The schedule was discussed with Keystone so they can be
aware of the critical dates that their work must be completed by.
- Bob faxed and followed up with phone calls to the other
contractors so they will also have their scope of work done by the time the
scaffold is dismantled. September 13th on the West portico and September
20th on the North portico.
- Wallace Builders has the steel ordered for the North
portico slab to begin demolition.
ITEMS TO VERIFY
- The next meeting is Tuesday, September 7, 1999 at 10:00
a.m.
PROJECT: North & West Portico Restoration
REPORT NO. 22
Mercer County Courthouse
Mercer, Pennsylvania
DATE September 7, 1999 TIME
10:00 a.m.
PRESENT AT MEETING Jerry Johnson -
Former
Commissioners and President of Historical Society
Denny
Salmon - Wallace Builders
Lou
DeJulia - Mercer County Maintenance
Bob
Mastriana - 4M Company
NOTES
There was much discussion with Lou, Denny and Bob regarding
Keystone's additional work authorization, and after a conference call to John
Thiry at Keystone, we decided on the following:
- The North portico additional cleaning is projected to be
$2,767.00 of which we felt approximately $500.00 was acceptable. The
West portico additional cleaning is projected to be $3.049.00 which
we felt was fair due to the extensive number of cleanings required and the
difficulty the West portico entailed.
- Regarding possible overtime wages - 8 man days projected
for overtime was figured which is approximately $1,000.00. We decided to
delay approving this until we see what time is actually incurred.
- Applying two coats of Miracote to the West portico columns
and bases is necessary due to the continual bleeding of the iron oxide and
the unsightly appearance of the columns. The projected cost of 2.000.00
is to be approved.
- Keystone estimated 60 buckets of Jahn stone restorer in
their original proposal, however 30 additional buckets were needed. The estimate
was based on 1/2" deep patches with 1/4" waste. Extensiveness of
the depth of the patches was unknown at that time. The estimate was accurate
as far as area takeoffs, however the depth of the patches was much greater
than anticipated. We felt that we should share equally in this additional
cost so we agreed to pay $3.000.00.
- The total work authorization presented by Keystone is
$15,000.00 plus the contractors mark-up of 10% which totals $16,500. The
amount we negotiated, which all parties feel is fair, is $8,549.00 plus a
10% mark-up for Wallace Builders of $851.00. Thus the total change order #2
to be entered into with Wallace Builders in the future regarding Keystone,
not including any overtime, is $9,400.00 which saves the county approximately
$7,100.00.
ITEMS TO VERIFY
- The next meeting is Thursday, September 9, 1999 at 10:00
a.m.
PROJECT: North & West Portico
Restoration
REPORT NO. 23
Mercer County Courthouse
Mercer, Pennsylvania
DATE September 9, 1999 TIME
10:00 a.m.
PRESENT AT MEETING Rick Boggs - Chief Clerk
Lou DeJulia - Mercer County Maintenance
Kevin Klosky -
Keystone Waterproofing
Bob
Mastriana - 4M Company
NOTES
GENERAL
- Lou and Bob met with Rick Boggs to update him regarding
Keystone's additional work authorization proposal. Wallace Builder's will
submit this as part of Change Order #2, which is to be presented to the
Commissioners as the extent of the additional work is finalized.
WEST PORTICO
- Keystone cleaned the upper stone balustrade prior to
sealing the masonry and asked for approval to proceed. Lou and Bob told
Kevin it is still not acceptable and to re-clean due to the iron oxide
staining. Calls were made to Tom Auel and to Keystone regarding the
re-cleaning. Dave Sebek will be at the Courthouse on Friday with Kevin to
re-clean.
- The plasterers are finishing the moldings on the portico
ceiling and should be completed by Friday.
- The scaffolding is scheduled to be dismantled on Monday,
September 13th as planned.
ITEMS TO VERIFY
- The next meeting is Thursday, September 14, 1999 at 10:00
a.m.