|
PROJECT: North & West Portico Restoration
REPORT NO. 12
Mercer County Courthouse
Mercer, Pennsylvania
DATE July 29, 1999 TIME
9:30 a.m.
PRESENT AT MEETING Ed Sferra - Federal Iron
Works
Lou DeJulia - Mercer County Maintenance
John
Thify - Keystone Waterproofing
Kevin
KIosky - Keystone Waterproofing
Bob Mastriana - 4M Company
NOTES
- Lou and Bob met with Ed Sferra of Federal Iron Works to
review the unstability of the 3rd floor railings. It was determined that
since they are unstable only at the midpoint of the rotunda span, two sets
of double brackets should be added to each railing at quarter points to
stiffen the horizontal movement of the railing. Ed field measured the
brackets and will give Lou a proposal to fabricate and install the sixteen
brackets.
- Federal Iron Works also field measured the exterior
railings necessary for the North and West portico and reviewed with Lou and
Bob the historic drawings in order to replicate accurately the railings. Ed
will begin the shop drawings and forward them to Bob and Lou for approval.
- John Thiry of Keystone brought the other Jahn stone mortar
samples for the more gray colored stone, dominant in the portico foundation
bases. Three samples were reviewed and the one chosen, which matched
perfectly, was Jahn 246-SS-3. Keystone was given the approval to order this
material. This completes the two colors needed to blend with the variations
in the stone masonry of the courthouse.
- The North portico stone repairs will be completed in two
weeks and the West portico in one week.
- The interior pointing of the North portico has begun and
looks excellent
- The cleaning of the North portico interior is finished and
they are approximately one quarter done with the cleaning of the columns.
- Keystone did five applications of cleaning on the five
stones of the North portico pediment that was badly stained. It was agreed
that they finally look acceptable so they were given approval to begin the
repointing.
- Keystone is doing all their work on the interior of the
porticos so Easley and Rivers, the plastering contractor, can get started with
their demolition. Keystone will then finish the exteriors while Easley and
Rivers finish the interiors in order to expedite the job and the time for
the rental of the scaffolding.
ITEMS TO VERIFY
- The next meeting is August
3, 1999 at 10:00 a.m.

PROJECT: North & West Portico
Restoration
REPORT NO. 13
Mercer County Courthouse
Mercer, Pennsylvania
DATE August 3, 1999
TIME 10:45 a.m.
PRESENT AT MEETING Doug Wallace -
Wallace Builders
Bob Mastriana - 4M Company
NOTES
- Lou is on vacation so he couldn't be present. Lou's
assistant was available for discussion.
- Doug and Bob reviewed and signed monthly payment requests
and submitted them to Rick Boggs to
review with Lou next week.
- The 4M Company also submitted an invoice for work completed
to date.
- Easley & Rivers completed the demolition of the West
portico ceiling on Friday and Monday and also began demolition on the North
portico ceiling which should be completed this week Easley & Rivers must
provide protection for their work so as not to cause damage to the restored
stonework
- Keystone is continuing on the Jahn stone restoration
sculpting new pieces to replicate the badly deteriorated stone. The West
portico should be done by Monday.
- Repointing is continuing on the North portico pediment and
interior wall. Additional cleaning of the columns is continuing after hours.
- Federal Iron submitted the shop drawings for the railing
replacement approval. The design is good but the profiles of the top rail
and diagonal bracing need reworked to match the historic profile better.
They are to re-submit.
- Roof Rite is coming next Monday to repair the West portico
scuppers and downspouts.
ITEMS TO VERIFY
- The next meeting is
August 5, 1999 at 1:30 a.m.
PROJECT:
North & West Portico Restoration
REPORT NO. 14
Mercer County Courthouse
Mercer, Pennsylvania
DATE August 5, 1999
TIME 1:15 p.m.
PRESENT AT MEETING
Chip Smith - Easley & Rivers
Doug
Wallace - Wallace Builders
Bob Mastriana - 4M Company
NOTES
-
Doug Wallace and Bob Mastriana met with Chip
Smith of Easley & Rivers, the Plastering Contractor, to discuss the
condition of the plaster ceiling moldings.
-
Many of the plaster moldings are deteriorated
beyond repair. Interior plaster was used on the exterior, which is molding
plaster and lime, and the 90 years of exposure has taken its toll.
-
For the flat ceiling surfaces, cement plaster
was used to bond to the cement ceiling surfaces which is the preferred
plaster material for exterior use. However, for the decorative plaster
moldings to match, the same type of molding plaster must be used. The
Contractor will try to clean the existing plaster to match the new sections
without use of any low pressure water cleaning techniques so as to not
further damage the delicate plaster moldings.
-
Easley & Rivers will search the
manufacturers catalogues for plaster moldings to try and match the historic
profiles. If they can't be matched, we will try to replace the missing
moldings with ones removed from other ceiling areas and then replace those
with something as similar as possible.
ITEMS TO VERIFY

Back
to Main Page Next
|